The crashing credit market — which has affected Centaur’s casino plans — is now delaying Mahoning Township’s sewer line project
The township supervisors last night announced they will hold $8 million worth of sewer bids for 60 days, which is allowed by law. In that time, they want to meet with officials from Indiana-based Centaur Inc. to determine the status of Valley View Downs, the $455 million racetrack/casino complex proposed for Mahoning Township.
Last fall, Centaur was awarded the state’s final harness racing license, then applied for a casino license to operate up to 3,000 slot machines.
However, the investigation, the refusal of the Pennsylvania Gaming Control Board to award a conditional license, and the collapse of the credit market caused Centaur to default on an almost-$1-billion loan. The project is on hold until Centaur obtains financing, new partners or explores alternatives that may include selling its property, harness license or interest in the project.
The supervisors also plan to negotiate with the contractors to determine if they will extend the time they will hold their bids. In addition, the supervisors said, funding is not yet in place.
Gary Pezzuolo, supervisor chairman, said bids had been opened Sept. 30 for the sanitary sewer project. The apparent low bidders are:
•A.P. O’Horo of Youngstown, general contractor, $6,117,000, lowest of four bids
•Intertech of Lowellville, Ohio, electrical contractor, $1,683,300, lowest of five
•Central Heating and Air Conditioning of New Castle, $212,327, heating contractor, lowest of four.
MULTIMILLION PROJECT PROPOSED
The township proposed a $22.7 million project that includes a wastewater treatment facility with the capacity to process 360,000 gallons per day, more than 100,000 feet of pipeline and six lift stations. The facility, to be located off Route 224, would serve residents of Edinburg, Hillsville and the Valley View complex.
Pezzuolo said the township had anticipated completing the plant and sewer lines so it would be ready when the track opened in July 2009.
After financial problems began, the Pennsylvania Harness Racing Commission in August granted Centaur a one-year extension, giving it until July 2010 to begin racing at Valley View Downs.
If new funding can’t be obtained, and if the track and casino are put on hold, Pezzuolo said, the supervisors will proceed, but scale back the facility.
Without the track, he said, the township will require a plant capable of treating 160,000 gallons per day to accommodate the township’s 600 residents of Hillsville and Edinburg.
FUNDING JEOPARDIZED
Following the meeting, Pezzuolo explained that without the track and casino, the township’s funding also is in jeopardy.
In July, the Pennsylvania Infrastructure Investment Authority agreed to provide almost $10 million through a 1 percent loan to be repaid over 10 years. However, Pezzuolo said, about $7 million of that was received because 2,500 jobs — construction and full-time and part-time jobs after the facility opens — were to be created.
“They will not release the money if the jobs are not created,” he said.
This prompted a resident to ask if extravagant tap-in fees are to be expected if Valley View does not materialize.
Pezzuolo said that would not happen.
He and Supervisor Francis “Poncho” Exposito remain confident the track and casino will go to the township.
“They have a lot invested in the project,” Pezzuolo noted, including property, plans, engineering and permits.
“If they can get the financing, I’m confident Centaur will build. If not, they will sell. But I’m sure we’ll see the project built here.”
Exposito proposed the supervisors and Lawrence County commissioners meet with representatives of Centaur and the governor’s office “to get answers.”
TIME FOR FUNDING
Pezzuolo said he did not believe such a meeting would be productive noting, “Centaur got a year to raise money.”
Like Pezzuolo, Exposito said he believes “even if the property is sold, it will go to someone interested in constructing a track here.”
He also noted Centaur already contributed $300,000 toward the sewer project.
“They gave us the $300,000 in good faith as a portion of their tap-in fee,” Pezzuolo said.
Asked by a resident if the township is under order by state officials to install sewer lines within a specified time, the supervisors said state officials know their situation with Centaur and are working with them.
TOP STORIES
ON HOLD: Centaur hardships delay Mahoning sewer project
- TOP STORIES
-
-
Towne Mall Memories, Part 1: Former merchants recall glory days when center teemed with shoppers, excitement
In the early 1970s, there was only one place to go for pizza and a perm. The Towne Mall. Today, you can still satisfy your cravings for a hair style and a New York style under that same, single roof. Only now, the place is called the Cascade Galleria, and the name isn’t the only thing that’s changed.
-
Road to the Mall: Some former merchants tell how and why they decided to locate in the facility
They came at various times but for the same reason. They wanted to be a part of the Towne Mall. When Sears became the first mall store to open in 1969, others quickly followed. All but one of those original mall merchants — Madelyn Rice of the Towne Mall Beauty Salon — are long gone from the facility now called Cascade Galleria.
-
Fire again hits former Shenango China plant
Black smoke billowed from the shell of the former Shenango China plant Friday afternoon. As temperatures flirted with 90 degrees, firefighters from seven companies operated as relay teams to knock back the fire, which firemen believe was deliberately set on the second floor at the back of the property.
-
New Castle district gives early budget highlights
Balancing of the New Castle Area School District’s 2012-13 budget will not require a property tax increase.
The school board has called a special meeting for 6 p.m. Tuesday to introduce its spending plan totaling $40,538,389 for next school year. That represents a 3.7 percent or $1,461,942 increase from this year’s budget. -
Car splits pole in Neshannock crash
A New Castle man suffered injuries in a Neshannock Township accident yesterday where his car hit a pole and overturned. Neshannock police reported that Christopher Story, 39, no age given, of 411 Park Ave., hit another car from behind while traveling on Maitland Lane around 5:20 p.m.
-
New with a view? Commissioners hope to see water from bridge
The Lawrence County commissioners want to see rocks and rippling waters when crossing the North Street Bridge. In other words, a view of the Neshannock Creek is something they want built into the plans for replacement of the bridge.
-
Photo Gallery, Story: Hometown to remember Medal of Honor winner
Army Spc. Leslie H. Sabo Jr. has been fittingly honored in Washington, D.C. for his ultimate sacrifice in Cambodia. Now, his home town and county of Lawrence want to bestow more accolades on the Medal of Honor recipient, who was killed while protecting his platoon in battle May 10, 1970 in the Vietnam War.
-
Transit authority suspends bus run to Ohio line, outlets
The New Castle Area Transit Authority has suspended a bus route to the Ohio line. Service in that direction is discontinued at least for the summer, but perhaps longer. Leonard Lastoria, authority general manager, attributes the suspension to a lack of manpower.
-
Finale: Longtime band director Gary Taylor ready to call it a career
This fall, the Wilmington High’s band performances no longer will be Taylor made. Director Gary Taylor has announced his retirement after 32 years of holding the baton for the school district. Taylor capped his career with the band marching in the Kentucky Derby parade earlier this month, and was honored at a retirement gala at the home of attorney Dallas Hartman.
-
Photos, Full Story: Annual Relay for Life attracts hundreds to Shenango High
Hundreds of area residents lined the Shenango High School track Saturday to kick off this year’s Relay For Life festivities. The theme of the event was, “Lights, Camera, Relay,” and the stadium fence was filled with stars.
- More TOP STORIES Headlines
-